Alen Gas Project Prepares for Early 2021 Start-up

Noble Energy’s Alen natural gas project offshore Equatorial Guinea remains on track for a 2021 start-up.

The project’s offshore pipeline installation, which will span 43 miles and have the capacity to transport 950 million cubic feet of natural gas per day, is on schedule for Q3 2020, with final hookup and commissioning being implemented in late 2020.

The Alen gas project remains one of the few major African energy projects on schedule for completion, as COVID-19 continues to cut investment for capital-intensive projects,

The Alen field carries estimated recoverable reserves of approximately 600 billion cubic feet of natural gas. Gas from the field will be fed to the onshore Punta Europa gas complex, which houses LPG, methanol and LNG processing facilities, in an effort to create an offshore LNG hub in the Gulf of Guinea.

Share This Article

Share on twitter
Share on facebook
Share on linkedin
Share on reddit
Share on whatsapp
Share on email
Shuaib Van Der Schyff

Shuaib Van Der Schyff

A Digital Marketing Coordinator, and a Graduate from the University of Cape Town with a Bachelor of Arts Degree in Media Studies and English Literature.

Subscribe to our newsletter

Sign up for latest news and event info

Copyright © 2021 Energy Capital & Power. Privacy Policy · Terms of Use